Keeping a construction site on schedule
Client: Ashcourt Group
Location: Durham, England
Sectors: Construction
The Challenge
Fast drying a wet winter building site
A little rain never hurt anyone but a lot of bad weather can spell time delays and budget blowouts for a construction site. Ashcourt called us when they found themselves behind schedule on the construction of four student accommodation buildings. The interior had been exposed to the extremes of a Durham winter causing site workers frustrations and delay.
Project Fact File
The Solution
One modular mobile system for four buildings
We packaged up a 125 kW heater and ducting connected to a 30 kVA generator. This was linked to a 1,000 litre fuel tank to minimise the footprint. Because the equipment was modular and easy to move, we only needed one heater to dry out all four buildings.
Project Manager , Ashcourt Group
Matt Tinker
The Impact
Project schedule and winter weather beaten
Despite the bad weather, the project was delivered ahead of schedule. Savings were made by only having to hire one effective modular heater for all four buildings. By rolling the power and temperature control into one package, the customer needed to manage only one supplier, one point of contact and invoice, saving on coordination tasks and administration time.